Welcome the construction information website for Minto Communities new condominium The Saint, at 89 Church Street in Toronto. Our most recent construction updates below. For all our updates please click here or select Construction Updates in the menu above.

Crane Lights at the Saint

Crane Lights at the Saint

Crane Lights at the Saint. Please Note: Our regular construction update will be posted on Friday September 1, 2023.   Crane Lights:  Unfortunately the concrete finishing crew left on the overhead light from the crane at The Saint. Minto's construcion management...

read more
August 18 Construction Update for the Saint.

August 18 Construction Update for the Saint.

The Saint: work set to begin for the 25th Floor next week.  Saturday Work: There will be a crew on this Saturday, August 19, carrying out a variety of tasks.   Outlook for the week of August 21 - August 26: Crews will be pouring concrete for level 25 this week. Window...

read more
August 11 Construction Update for the Saint

August 11 Construction Update for the Saint

The Saint: work begins on the 24th Floor next week.  Saturday Work: There will be a crew on this Saturday, August 12, carrying out a variety of tasks.   Outlook for the week of August 14 - August 19: Crews will begin working on forming, rebar installation and concrete...

read more
August 4/23 Construction Update

August 4/23 Construction Update

The Saint: work on the 23rd Floor to be completed next week.  Saturday Work: We do not expect significant work on site this holiday weekend, i.e. Saturday, August 5, though there may be some modest activity on the site. The site will be closed Monday, August 7 for the...

read more
July 28 Construction Update

July 28 Construction Update

The Saint: work on the 23rd Floor set for the coming week.Saturday Work There will be a crew on site, Saturday, July 29, working on a variety of tasks throughout the site.    Outlook for the week of July 31 - August 4 Crews will begin working on rebar installation,...

read more