Welcome the construction information website for Minto Communities new condominium The Saint, at 89 Church Street in Toronto. Our most recent construction updates below. For all our updates please click here or select Construction Updates in the menu above.

Construction Update for January 13, 2023

Construction Update for January 13, 2023

Construction Information -- Moving ahead on the 9th Floor at the Saint.  Work next week at the Saint: Pouring the Level 9 concrete slab floor is set to get underway this coming week.   2 rebar (steel) deliveries and 2 concrete deliveries are scheduled for the week....

read more
The Saint December 12 – 16, 2022

The Saint December 12 – 16, 2022

Work to begin on the 8th Floor at the Saint.  Construction Outlook for the week of December 12:   The vertical columns and walls rising from the 7th Floor are set to be completed early this week.  The initial concrete pours for the 8th Floor slab are set to get...

read more
Construction Update – December 2, 2022

Construction Update – December 2, 2022

Construction InformationWork progressing on the 7th Floor at the Saint.  Saturday Work - December 3 There will be a crew on site this Saturday. They will be doing prepartion work for next week's Level 7 concrete work. We expect they will also be doing a number of...

read more
Construction Update – November 24, 2022

Construction Update – November 24, 2022

Construction Liaison Meeting today. Update for Saturday ... REMINDER - Construction Liaison Meeting Today - November 24 at 3 pm via ZOOM If you have not received a link yet please email us at contact@thesaintconstruction.info Construction Update:  The Saint is now...