Welcome the construction information website for Minto Communities new condominium The Saint, at 89 Church Street in Toronto. Our most recent construction updates below. For all our updates please click here or select Construction Updates in the menu above.
Update for the Saint, as of July 5, 2022
July's Construction Liaison Meeting this Thursday at 3 pm. Update for the week: No Saturday work this week, i.e. no work on July 9. Currently crews are working on vertical columns and walls rising from the Level 2 slab floor, this will be ongoing until the end of the...
Update for the week of June 27, 2022
This week the main focus of work on the site will be completing the 2nd floor concrete slab floor. Once that is done, work will begin on forming and pouring the vertical columns that rise from the 2nd floor slab. This will mean that there are daily concrete deliveries...
New Date for the Construction Liaison Mtg. + Update for June 20, 2022
The Construction Liasion Meeting is rescheduled to July 7. Update for the week: We can confirm that the East Gate for the site is scheduled to be installed today. The East Gate, which will be the second gate entrance to the site and it will facilitate the efficient...
Outlook for the Week of June 20, 2022
Outlook for the week of June 20, 2022 Work will continue on forming, pouring and finishing sections of the 2nd Floor this coming week. The East Gate, which will be the second gate entrance to the site, may begin being installed on Monday, June 20th. While we still...
May Construction Report + Outlook for the Week of June 13, 2022
Construction Highlights as of May 31, 2022: As much work as possible continued through May, with the strikes by LiUNA and the Carpenters Union interrupting progress on forming and concrete work. We held our May Construction Liaison Meeting (CLM) on May 26th at 3 pm...
Weekend Update for the Saint
Saturday Work at the Saint. Saturday June 4, 2022 Crews will be on site this Saturday, to take down the West Gate, the current gate into the site that is adjacent to Church Street. This is being done to facilitate the installation of the interim hoarding strategy for...
Update for the Saint, June 2, 2022
Work on the mezzanine level continues at The Saint. Looking ahead through the week of June 6, 2022 The main focus of work this past week and through the coming week of June 6th, is the ongoing build out of the mezzanine level of the Saint. This involves ongoing...
Update for the Saint, May 27, 2022
Concrete and Form Work underway again at the Saint. Looking ahead through the week of May 30, 2022 LIUNA form-workers & crane operators were back on the site as of Tuesday, May 24. Work has resumed on forming, pouring and finishing the mezzanine level of the...
Activity Resumes at the Saint. Construction Liaison Meeting – Thursday, May 26
LIUNA formworkers back on the job at the Saint. Week of May 24, 2022 - Update LIUNA form-workers & crane operators are back on the job this week. While the Carpenters Union remains off work this week, having form-workers and crane operators back on the job allows...
April Construction Report + Current Site Update
Construction InformationThe April Construction Summary Report is now available.Site work for the coming week, May 16 - 20 Both the Carpenters’ Union and LIUNA, the Laborers’ International Union, remain on strike this week. There is also the prospect of additional...
Strikes slow work this week at the Saint construction site.
Impact of the LIUNA & Carpenters Union job actions continue. Week of May 9, 2022 LIUNA, the Laborers’ International Union, remains on strike this week. LIUNA covers workers who do high-rise forming, self-levelling forming, tile, railing, carpet, and hardwood...
Mid Week Update: Labour action slows work at the Saint.
Impact of the LIUNA job action felt at the Saint. Mid-Week Update LIUNA, the Laborers’ International Union, is currently pursuing a job action. This means that the formworkers and crane operators are effectively on strike. Construction management at the Saint are not...