Welcome the construction information website for Minto Communities new condominium The Saint, at 89 Church Street in Toronto. Our most recent construction updates below. For all our updates please click here or select Construction Updates in the menu above.

March 15 Construction Update for the Saint

March 15 Construction Update for the Saint

Preparation work for Level 48 continues through the week of March 18. Saturday Work Crews will be on site Saturday, March 16, doing a variety of tasks to set up next week's work plan. Current Construction  Status  Concrete work has been completed for Level 47. The...

read more
March 1 Construction Update for the Saint

March 1 Construction Update for the Saint

Crews will completing Level 47 the week of March 4.  Saturday Work Crews will be on site Saturday, March 2, doing a variety of tasks to set up next week's work plan. Current Construction  Status  Concrete work is partially complete on Level 47. The last residential...

read more
The Saint – February 9, 2024, Update

The Saint – February 9, 2024, Update

The Saint will begin work on the 45th storey next week. Saturday Work A crew will be on site this Saturday, February 10, doing a variety of tasks.   Current Construction  Status  Concrete work on Level 44 is substantially complete today. The Curtain Wall...

read more