Welcome the construction information website for Minto Communities new condominium The Saint, at 89 Church Street in Toronto. Our most recent construction updates below. For all our updates please click here or select Construction Updates in the menu above.

Saint Update for August 30, 2024

Saint Update for August 30, 2024

Roof work & Landscaping work on Church Street are ongoing.  Labour Day Holiday The site will be closed on Monday, September 2, for Labour Day. Work will resume on Tuesday, September 3.  Saturday Work   Once again, work crews will be on site Saturday, August 31,...

read more
Saint Construction Update for July 19, 2024

Saint Construction Update for July 19, 2024

Roof level work continues at the Saint.  Saturday Work Once again, work crews will be on site Saturday, July 20, doing a variety of tasks to set up the following week's work plan.  Updates:  The site now has access to its permanent power supply.  The crane will remain...

read more
The Saint Construction Update, July 12, 202

The Saint Construction Update, July 12, 202

Work is still proceeding on the roof level at the Saint.  Saturday Work Once again, work crews will be on site Saturday, July 13, doing a variety of tasks to set up the following week's work plan.  Updates:  The site now has access to its permanent power supply.  The...

read more
Construction Update June 21, 2024

Construction Update June 21, 2024

Work on the roof level is ongoing. Saturday Work Once again, work crews will be on site Saturday, June 22, doing a variety of tasks to set up the following week's work plan. This week's construction outlook,June 24 - June 28: Roof concrete work ongoing. Curtain wall...

read more