Welcome the construction information website for Minto Communities new condominium The Saint, at 89 Church Street in Toronto. Our most recent construction updates below. For all our updates please click here or select Construction Updates in the menu above.

June 2 Construction Update

June 2 Construction Update

Work this Saturday, June 3 at the Saint. June 3, 2023: There will be a crew on-site this Saturday working on preparation for next week and general housekeeping tasks. Work Outlook for the week of June 5 - June 9:  Crews are continuing to work to complete the Level 17...

read more
May 26 Construction Update

May 26 Construction Update

Construction Liaison Meeting - Rescheduled to June 1.Saturday Work There will be a crew on-site this Saturday, May 27 working on preparation for next week and general housekeeping tasks. Work Outlook for the week of May 29 - June 1:  Crews will start the Level 17...

read more
May 19 Construction Update

May 19 Construction Update

Construction Liaison Meeting - May 25 Our next Construction Liaison Meeting is scheduled for Thursday, May 25 at 3 PM A link for the Construction Liaison meeting will be emailed out on Wednesday, May 24 for all who may wish to attend. Saturday and Victoria Day Weekend...

read more
May 12, 2023 – Update

May 12, 2023 – Update

Saturday Work, May 13.Outlook for the week of May 15.Update: There will be a crew on site this Saturday, May 13 working on preparation for the coming week and general housekeeping tasks throughout the site.  Overall:  Window work remains at Level 6. The concrete for...

read more
April 10 Construction Update

April 10 Construction Update

13th Floor underway at the Saint.  Concrete Update: Work on the 13th Floor concrete slab continues to the the prioirty this week.  This involves forming, setting rebar, pouring concrete and then finishing that poured concrete. Concrete and rebar deliveries will...

read more
Site closed for the Easter Weekend.

Site closed for the Easter Weekend.

Construction InformationSite Closed Friday, April 7 thru Sunday, April 9. The Saint construction site will be closed for the Good Friday statutory holiday, on April 7. There will be no work scheduled for Saturday, April 8. Site construction work will resume at 7:00 AM...

read more