Construction Update for June 4, 2021

Construction Update for June 4, 2021

Excavation has reached the P6 Level at The Saint. This week has seen a key milestone reached excavation work has reached the final underground level -- P6 -- of what will be the underground parking floors of the Saint. There will be no work on site tomorrow, Saturday...

read more
Update for Construction at the Saint

Update for Construction at the Saint

Excavation continues at the Saint. Crane delivery rescheduled. Excavation, including some drilling work will continue today, May 6 and Friday, May 8. There will be some noise from this work during construction hours. The planned delivery of the large mobile crane has...

read more
Construction update for May 3, 2021

Construction update for May 3, 2021

Drilling work and the delivery of a large mobile crane expected this week at the Saint. As part of the next phase of excavation, some drilling will commence this week. There will be some noise from this work during construction hours. Also, a large mobile crane is...

read more
Midweek Construction Update

Midweek Construction Update

Excavator Removal Wednesday, April 28. Small Mobile Crane Delivery Thursday, April 29. Steady progress has been made on the excavation of the site at 89 Church Street.  UPDATE: The long-reach excavator, depicted in use above, will now be removed from the site on April...

read more