by admin | Jul 31, 2020 | Construction Updates
The covered walkway is now up on Church Street. This walkway will provide pedestrian protection during the demolition of 97 Church Street, the former Florentine Restaurant, which remains scheduled to get underway this coming month. Once we have precise dates will...
by admin | Jul 30, 2020 | Construction Updates
Demolition contractors continue to work on abatements to the structures at 97 and 99 Church Street, prior to the beginning of demolition work. This abatement work will continue for about this week and likely into early next week. This week the demolition contractor...
by admin | Jul 24, 2020 | Construction Updates
Pre-Demolition work was ongoing at The Saint this past week and will continue into next week. There will be crews on site throughout the week of July 27. We will have a more detailed update next week. Demolition of 97 Church Street, the former Florentine Restaurant,...
by admin | Jul 13, 2020 | Construction Updates, Events
Please join us on Tuesday, July 21 at 6:30 pm for an online information session that will outline the initial phases of construction at Minto’s The Saint, 89 Church Street. As our construction start approaches, we would like to invite you to an information...
by admin | Jul 12, 2020 | Construction Updates
The initial phase of pre-demolition work is set to get underway on Monday, July 20, at 7:00 am. This work will involve a variety of activities necessary to prepare for the demolition of the existing low-rise buildings on the northern section of the site. To find out...