The Saint Construction Update – 9/23/20

The Saint Construction Update – 9/23/20

Demolition is entering the final phase.   The machine demolition 99-97 Church Street is almost complete at the Saint construction site. Starting tomorrow, Thursday, September 24th, the demolition contractor will be backfilling the hole where the basement...
97-99 Church Structure Demolished Above Grade

97-99 Church Structure Demolished Above Grade

99-97 Church demolished above grade. The removal of the above-grade portions of the existing building at 99-97 Church Street was substantially completed today. The next phase of work by the demolition contractors will focus on clean up and work on the basement levels...