by admin | Oct 28, 2020 | Construction Updates
Crane set to arrive on site Thursday, October 29, 2020. The site at 2:30 pm, October 28, 2020 Currently scheduled for tomorrow, Thursday October 29: The shoring contractor is scheduled to have a crane delivered to the site. The construction management team is also...
by admin | Oct 23, 2020 | Construction Updates
Backfilling at the Saint after ‘daylighting’ completed. This past week, crews exposed — ‘daylighted’– the Bell lines that run along Church Street. The work did take a little longer than expected due to the rain days which made...
by admin | Oct 17, 2020 | Construction Updates
Construction Look Ahead for The Saint. There is no work on site for the weekend of October 17 – 18. Work resumes on Monday, October 19, and will the continuation of the “daylighting: process for the Bell Canada lines along Church Street. Monday morning...
by admin | Oct 14, 2020 | Construction Updates
Excavation continues at The Saint this week. Excavation work is ongoing at the Saint construction site in preparation for the setup of the drilling rig that is expected to get underway in the coming days. Starting tomorrow, Thursday, October 15, the utility lines...
by admin | Oct 9, 2020 | Construction Updates
Digging on site today. Drilling platform to be installed mid-month at 89 Church Street. There was drilling on site today. Work will pause for the Thanksgiving Weekend and resume on Tuesday, October 13. We expect work to begin on the construction of the drilling...