Construction Look Ahead for The Saint.
There is no work on site for the weekend of October 17 – 18. Work resumes on Monday, October 19, and will the continuation of the “daylighting: process for the Bell Canada lines along Church Street.
Monday morning will see more hydrovac excavation. Bell Canada representatives will inspect the area and adivse when sufficeint work has been done.
Once this work is completed, the area will be backfilled. The next step will be preparations for the arrival of the shoring contractor. We expect the initial phase of shoring work to get underway either late next week or on Monday Ocotber 26th.