by admin | Mar 29, 2021 | Construction Updates
Excavation is the key focus of work this week at the Saint. Tieback installation was completed last week. Work on the site this week will include digging, excavating and hauling away excavated soil. The long-reach excavator, that was delivered to the site last...
by admin | Mar 25, 2021 | Construction Updates
Long reach excavator arrives on the site tomorrow, Friday, March 26 Tieback installation has been completed. For the next phase of excavation a long reach excavator will be used to dig and load hauling trucks. After it arrives on Friday, it will remain on site until...
by admin | Mar 24, 2021 | Construction Updates
The tieback machine was removed from the Saint construction site today, March 24. The tieback machine that has been in use over the past several weeks, was removed from the site today. In order to lift it out of the excavated site, a mobile crane was required....
by admin | Mar 22, 2021 | Construction Updates
Church Street sidewalk repairs underway today through tomorrow, March 23. This morning, Monday, March 22, repair work to the Church Street sidewalk got underway and will continue through the afternoon. We expect it the repair work to be completed tomorrow, Tuesday,...
by admin | Mar 19, 2021 | Construction Updates
Excavation of the Saint construction site continues to make progress. As the week comes to a close, the progress of excavation at 89 Church Street is clearly visible when viewed from above. The program for the week of March 22, the first week of spring, will follow...