Excavation of the Saint construction site continues to make progress.
As the week comes to a close, the progress of excavation at 89 Church Street is clearly visible when viewed from above.
The program for the week of March 22, the first week of spring, will follow the pattern of the past few weeks: excavation, soil removal via dump trucks, and tieback installation. We note that the crews will be doing repairs to the Church Street sidewalk next week. And just in case, as spring weather in Toronto is typically unpredictable, the snow removal contract for the site will be kept in place.
NOTE: There will be no work this Saturday, March 20.