Construction Update for the week of April 12, 2021

Construction Update for the week of April 12, 2021

by admin | Apr 12, 2021 | Construction Updates

Excavation has reached the P4 level at the Saint.  Work on the site this week will once again focus on the two key elements of the excavation process: digging out soil and then hauling away that excavated soil. The long-reach excavator, seen in the photo above, will...
Construction Update for the Saint for the week of April 5th 2021

Construction Update for the Saint for the week of April 5th 2021

by admin | Apr 5, 2021 | Construction Updates

Digging out the site continues throughout this week. Once again work on the site this week will focus on the two key elements of the excavation process: digging out soil and then hauling away that excavated soil. The long-reach excavator, seen in the photo above, will...

Archives

  • April 2021
  • March 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • July 2020
  • June 2020
  • Home
  • Construction Updates
  • FAQ
  • The Project
  • Concrete Work
  • Contact Us
  • About

Local Links

  • Old Town Toronto
  • St. Lawrence Centre for the Arts
  • St. Lawrence Community Recreation Centre
  • St. Lawrence Market Neighbourhood BIA
  • St. Lawrence Neighbourhood Association
  • St.Lawrence Market
  • Canadian Stage Company
  • Friends of Berczy Park
  • Friends of St. James Park
  • Jamii Esplanade
  • Meridian Hall
  • Young Peoples Theatre