Work on site Saturday, April 17.

There will be crews on site to load in the long reach excavator (pictured above) that was temporarily removed on Friday afternoon. A flatbed tractor trailer will deliver the long reach excavator to the site entrance and Lombard and Church and it will be positioned on site.  It is expected that this will take not much more than 15 minutes. 

Next week’s work schedule will look very much like this past week: digging out and hauling away soil from the site as crews press on to the next level – P5 – on their way to reaching the P6 underground level.