Excavation work to continue through the week of May 24.

There will be no work on site this Saturday, May 22 and the site will be closed for the Victoria Day holiday on Monday, May 24. Excavation work will resume on Tuesday, May 25.
We do not expect any major deliveries next week. There will be ongoing drilling, excavating and hauling away soil off-site, as work continues through the P5 level.
Next month will see a new phase of work on site, which we will detail in upcoming posts.
Work will continue to start at 7 am on weekdays this week.
The time work ends each day may vary but will remain within the standard City of Toronto construction hours.