by admin | Jun 30, 2021 | Construction Updates
Workers on Site Canada Day. Crane installation & Lombard St. Road Closure on Saturday, July 3. Workers on site July 1. Work on Friday July 2. Road closure on Lombard Street and crane installation on Saturday, July 3. Today, Wednesday, June 30, the long-reach...
by admin | Jun 23, 2021 | Construction Updates
Steel arriving on-site Thursday, June 24. Concrete work on Friday & Saturday, June 25-26. Thursday, June 24 Tomorrow, Thursday, June 24, steel for the concrete crane pad will arrive on the site. This delivery will require temporary occupation of one lane on...
by admin | Jun 18, 2021 | Construction Updates
The next phase of work at the Saint is set to get underway. The excavation has reached the P6 level and excavation is essentially complete. There will be no work on site this Saturday, June 19. The Week of June 21st This coming week rebar and concrete will be arriving...
by admin | Jun 14, 2021 | Construction Updates
Excavation closing in on completion at The Saint. The construction management team expects that the excavation team should be able to reach the bottom elevation towards the end of this week. Hauling is also almost complete. We do not expect there to be any large...
by admin | Jun 4, 2021 | Construction Updates
Excavation has reached the P6 Level at The Saint. This week has seen a key milestone reached excavation work has reached the final underground level — P6 — of what will be the underground parking floors of the Saint. There will be no work on site...