Excavation has reached the P6 Level at The Saint. 

This week has seen a key milestone reached excavation work has reached the final underground level — P6 — of what will be the underground parking floors of the Saint.

There will be no work on site tomorrow, Saturday June 5. Next week there will be continued excavation and hauling from the site. No large deliveries are expected next week.

NOTE: Toronto Hydro is soon scheduled to begin work on Church Street to provide power to the construciton site. We are not bale to provide the precise timing of this because it is based on Toronto Hydro’s work schedule and will be managed by them. However, once this work is complete, the Saint’s construction team will install hoarding around the site.

Work will continue to start at 7 am on weekdays this week.

The time work ends each day may vary but will remain within the standard City of Toronto construction hours.