Excavation closing in on completion at The Saint.
The construction management team expects that the excavation team should be able to reach the bottom elevation towards the end of this week. Hauling is also almost complete.
We do not expect there to be any large deliveries this week.
Looking Ahead:
The Week of 21st will be focused on placing rebar and concrete for the crane pad, which means rebar and concrete deliveries. Once the pad has cured, the crane will be erected, which will require a temproary street closure on Lombard. This is tentatively scheduled for the weekend of July 2nd. We will post more information and more precise timing next week.
Work Hours:
Work will continue to start at 7 am on weekdays this week.
The time work ends each day may vary but will remain within the standard City of Toronto construction hours.