The next phase of work at the Saint is set to get underway.
The excavation has reached the P6 level and excavation is essentially complete.
There will be no work on site this Saturday, June 19.
The Week of June 21st
This coming week rebar and concrete will be arriving on site. Rebar will be lowered into the excavated site with the long reach excavator. Concrete will be lowered via a pump truck. We expect the concrete to be poured on Saturday, June 26.
Once the pad has cured, the crane will be erected,
Crane Setup
As we noted in our previous post, the crane is tentatively scheduled to erected over the weekend of July 2nd, July 3rd, and July 4th. There will need to be a temporary road closure on Lombard Street to ensure the safe load in and setup of the crane.
We will post more information on the detail of the crane work and the accompnaying road closure in our next posts.
Work Hours:
Work will continue to start at 7 am on weekdays this week.
The time work ends each day may vary but will remain within the standard City of Toronto construction hours.