Hauling continues as formwork gets underway at The Saint. 

The Site will be closed all weekend – July 31 – August 2, including holiday Monday. Work will resume on Tuesday, August 3.

Inclement weather this past week caused unavoidable delays at the site. Hauling away soil will continue into next week. Waterproofing work is also continuing at the lowest level of the site. 

The forming contractor is now working on the site, so the critical work of preparing the lower level of the site is ongoing despite weather setbacks. 

The crane will be in regular operation as required. 

Work Hours

Work will continue to start at 7 am on weekdays this week.

The time work ends each day may vary but will generally remain within the standard City of Toronto construction hours.