Concrete & site servicing work continues at the Saint.
No work on site this Saturday. Work will resume Monday, September 27.
The City of Toronto approved contractors are continuing their work is ongoing, occupying the western northbound lane of Church Street. Underground drainage work has been completed on the site.
Look Ahead for the week of September 27th.
- The City of Toronto servicing work will contine this week, with activity moving to Lombard Street after work on Church is completed.
- Pouring concrete slabs and verticles will be ongoing through the week.
- Concrete trucks will be supplying the site through each work day.