by admin | Oct 29, 2021 | Construction Updates
Concrete work & servicing work continue at the Saint. Saturday – October 30 There is no work scheduled for this Saturday. Work will resume on Monday, November 1. Progress to-date: Concrete work on the P5 level is completed and progress on the P4 level has...
by admin | Oct 22, 2021 | Construction Updates
Concrete work moves to the P3 Level as municipal servicing work continues on Lombard Street. Saturday – October 23 There is no work scheduled for this Saturday, October 23. Progress to-date: Concrete and rebar installation has been completed on the P4 slab. ...
by admin | Oct 15, 2021 | Construction Updates
Concrete work continues on the parking levels as hoarding installation & servicing work continue. Saturday Work – October 16 There will be crews on site this Saturday, October 16. They will be conducting light work and general housekeeping tasks. ...
by admin | Oct 12, 2021 | Construction Updates, Events
We are pleased to share the September Construction Report for The Saint, 89 Church Street: Please click here to download a PDF copy of the summary report. We have sent out a request to neighbouring building representatives, property managers and the St. Lawrence...
by admin | Oct 8, 2021 | Construction Updates
Overhead protection begins installation as site servicing work continues on Lombard St. No work on site this Saturday. Work will resume Tuesday, October 12. The City of Toronto approved contractors are continuing their work on Lombard Street. We are looking forward...