Overhead protection begins installation as site servicing work continues on Lombard St.
No work on site this Saturday. Work will resume Tuesday, October 12.
The City of Toronto approved contractors are continuing their work on Lombard Street. We are looking forward to the wrap up of this work so hoarding and overhead protection can be installed on Lombard Street face of the site.
Scaffolding for the overhead protection on Church Street is being installed and this will continue through the week after the Thanksgiving Holiday.
Crews have completed the P5 concrete floor slab and vertical columns and are now working on the P4 slab and columns.
Look Ahead for the week of October 12.
- The City of Toronto servicing work on Lombard will be active next week.
- Pouring concrete slabs and verticles will be ongoing through the week, aiming to complete the P4 level.
- Concrete trucks will be supplying the site through each work day.