Concrete work continues on the parking levels as hoarding installation & servicing work continue. 

Saturday Work – October 16

There will be crews on site this Saturday, October 16. They will be conducting light work and general housekeeping tasks.

 

Look Ahead for the week of October 18: 

  • The City of Toronto approved contractors who are installing municipal services to the site, will be continuing their work on Lombard Street through next week, October 18 – 22.
  • The installation of hoarding and overhead protection will continue through next week on Church Street. 
  • The onsite crew will be working to complete the P4 level concrete slab and vertical columns. This will see concrete trucks delivering to the site daily through the week.
The September Construction Report for The Saint, 89 Church Street is available: 
Please click here to download a PDF copy of the summary report.