P1 concrete slab set to be completed the week of December 13

Saturday, December 11:

  • We expect that crews will be on site this Saturday, doing a variety of preparation work for next week and some general set housekeeping work.

    Progress to-date:

    • Concrete work on the P2 vertical columns are completed.

    Look Ahead for the week of December 6th 

    • The P1 (Parking Level 1) slab is planned to be completed next week if the weather cooperates.  
    • Further work on the Lombard Street Hoardings remains on hold pending the completion of site servicing work by Enbridge and Toronto Hydro.
    • Until the hoardings and overhead protection are in place we ask that pedestrians use the south sidewalk on Lombard Street. 
    • Concrete work, rebar deliveries via flatbed, and concrete deliveries will continue daily through the week of December 13th.

    Our November Construction Summary Report is available to download
    by clicking here.