Happy New Year: Work resumes this week at the Saint. 

Work resumses at the Saint on Tuesday, Janaury 4, 2022

  • Work will resume on the P1A (Parking Level 1 – Section A)  concrete slab floor. 
  • At this time of year, weather conditions can affect construction schedules, so work may be delayed accordingly. 
  • Municipal servicing work that remains unfinshied is expected to resume. When we hav emore deails on this we will post and circulate them. 
  • Concrete deliveries will continue each day that concrete is being poured. 
  • The completetion of the hoardings and overhead protection remains set to get underway this month, if all the remaining site servicing work is completed. 

Please note:

Our next Construction Liaison Meeting will occur on Thursday, January 20, 2022 at 3 pm EST.

We will send out a meeting invitation 10 days prior to the meeting.