Steel Deliveries and Concrete Work set for the week of April 4. 

Work in progress at the Saint.

Despite recent delivery challenges with the concrete supply, work has continued on the ground floor slab. The forming and pouring of vertical columns rising from the ground floor is underway. Concrete work will continue on site through the week of April 4, via standard concrete truck deliveries. 

Steel deliveries set for the coming week.

Two steel (rebar) deliveries to the site are scheduled for the coming week to support the ongoing concrete work. These deliveries are set for:

  • Tuesday, April 5
  • Thursday, April 7