by admin | May 27, 2022 | Construction Updates
Concrete and Form Work underway again at the Saint. Looking ahead through the week of May 30, 2022 LIUNA form-workers & crane operators were back on the site as of Tuesday, May 24. Work has resumed on forming, pouring and finishing the mezzanine level of the...
by admin | May 24, 2022 | Construction Updates, Events, Uncategorized
LIUNA formworkers back on the job at the Saint. Week of May 24, 2022 – Update LIUNA form-workers & crane operators are back on the job this week. While the Carpenters Union remains off work this week, having form-workers and crane operators back on the job...
by admin | May 13, 2022 | Construction Updates
Construction Information Contact Us Home Construction Updates FAQ The Project Concrete Work Contact Us About The April Construction Summary Report is now available. Site work for the coming week, May 16 – 20 Both the Carpenters’ Union and LIUNA, the Laborers’...
by admin | May 9, 2022 | Construction Updates
Impact of the LIUNA & Carpenters Union job actions continue. Week of May 9, 2022 LIUNA, the Laborers’ International Union, remains on strike this week. LIUNA covers workers who do high-rise forming, self-levelling forming, tile, railing, carpet, and hardwood...
by admin | May 4, 2022 | Construction Updates
Impact of the LIUNA job action felt at the Saint. Mid-Week Update LIUNA, the Laborers’ International Union, is currently pursuing a job action. This means that the formworkers and crane operators are effectively on strike. Construction management at the Saint are not...