July’s Construction Liaison Meeting this Thursday at 3 pm. 

Update for the week:

  • No Saturday work this week, i.e. no work on July 9.
  • Currently crews are working on vertical columns and walls rising from the Level 2 slab floor, this will be ongoing until the end of the week.
  • Next week will see the beginning of formwork for Level 3 slab floor. 
  • Engineers are reviewing pedestrian/vehicle study for the proposed protected Lombard Street crosswalk proposal

Construction Liaison Meeting this Thursday, July 7 at 3 pm.

If you would like an invitation to the meeting please email us at: contact@thesaintconstruction.info