by admin | Aug 26, 2022 | Construction Updates
3rd Level slab floor set to be completed this coming week. This coming week – construction highlights: We do not expect there to be work on-site this Saturday, August 27. The 3rd Floor Slab remains unfinished. Work proress this past week was unfortunately...
by admin | Aug 19, 2022 | Construction Updates
Work on Level 4 will be the focus for the coming week. This coming week – construction highlights: We have no confirmation of any work planned for Saturday, August 20 at the site, though there may be a small crew on-site doing prep work for the coming week,...
by admin | Aug 15, 2022 | Construction Updates
Construction Liaison Meeting – Thursday, August 18 at 3 pm. This Week – construction highlights: Rebar, forming and concrete work for Level 4. Deliveries through the week as needed. We do not expect late evening work this week but if that changes we will...
by admin | Aug 5, 2022 | Construction Updates
Saturday crew onsite August 6. The August 11 Construction Liaison Meeting is now, rescheduled to August 18. There will be work tomorrow, Saturday, August 6 at the Saint construction site, focused on preparing for next week’s continuing concrete and rebar work on...