4th floor work remains the focus at The Saint.  

Work at the Saint remains focused on the 4th floor, placing rebar (steel) into the forming structure, and then pouring Level 4 in sections. After each section is poured it will be finished to ensure it is level, smooth and sets properly. Finishing work may go into the late afternoon or early evening but it is not expected that work will go past 7 pm this week. 

The site crew is also starting to prepare for the installation of a construction hoist or external construction elevator. Part of this work has required the use of a hydrovac system as part of the necessary effort to check for buried gas lines and other city services. It has been particularly noisy, though still well within the permitted decibel levels for construction work. This part of the work is wrapping up and we do not expect to continue past Monday, September 26 at the latest. 

FILMING NOTICE – September 27

We have received a notice of filming and road occupation on Lombard Street for Tuesday, September 27, with filming preparation work scheduled for Sunday to Monday on September 25 & 26. 

The construction management will endeavour to work around this filming work with as little additional disruption as possible.