Weekend update + outlook for next week.

Weekend update + outlook for next week.

 Work set for Saturday, October 29, 2022.  This week work reached Level 6, as concrete and rebar work got underway on this level  after the completion of the 5th Floor. This Saturday: There will be crews on site doing work in preparation for next week’s rebar...
Construction Liaison Meeting this Thursday.

Construction Liaison Meeting this Thursday.

Construction Information Contact Us Home Construction Updates FAQ The Project Concrete Work Contact Us About   Work on Level 5 of the Saint progresses this week. The focus of work at the site this week will be rebar (steel) installation along with sectional concrete...
Saturday Work set for October 22, 2022

Saturday Work set for October 22, 2022

Construction Information Contact Us Home Construction Updates FAQ The Project Concrete Work Contact Us About Crew on site this Saturday, Oct0ber 22, 2022 Update: There will be crews on site doing work in preparation for next week’s rebar and concrete work.  We...
Update for Tuesday October 18, 2022

Update for Tuesday October 18, 2022

Construction Information Contact Us Home Construction Updates FAQ The Project Concrete Work Contact Us About   This afternoon will see large equipment on site to assist with concrete removal. After excavation work on Monday, October 17, was not able to complete the...
Work on level 5 this week at the Saint.

Work on level 5 this week at the Saint.

Construction Information Contact Us Home Construction Updates FAQ The Project Concrete Work Contact Us About   Pouring Level 5 at the Saint As the week begins the focus of work at the Saint is ongoing work to pour the 5th Level of the tower. This will involve a mix of...