Highlights of site activity this week. 

This week work will be focussed on the following: 

  • Crews will be working on the initial phases of the 5th Floor deck progressing from forming to pouring and finishing, 
  • The dock for the hoist (the external construction elevator) will be installed, starting at the 5th Floor Level.
  • The hoist car (the elevator car) will be delivered soon but we are not certain of the exact timing. Once we have confirmation we will post and circulate the information. 
  • There will be regular deliveries of concrete, materials and supplies as well as components for the hoist.

We do not expect late evening work this week but if this changes we will post and circulate an update.

REMINDER: The proposal to close pedestrian access to the north side of Lombard, and a City-standard, controlled crosswalk is being reviewed by City staff.

    The next Construction Liaison Meeting will be held on Thursday, October 27, at 3 pm via ZOOM.

    If you would like a link to the meeting please email us at contact@thesaintconstruction.info