This afternoon will see large equipment on site to assist with concrete removal.

After excavation work on Monday, October 17, was not able to complete the removal of some concrete that must be moved, it is anticipated that larger equipment will be needed. It is expected that this larger equipment will be deployed this afternoon. Once the concrete pieces are removed, we expect that the required additional equipment will also be removed from the site. 

There may be some temporary effect on traffic and pedestrian flows along Lombard Street while the additional equipment arrives and departs the site but we do not anticipate any significant impacts. 

Work will continue on the 5th Level of the tower during the workday.

The next Construction Liaison Meeting will be held on Thursday, October 27, at 3 pm via ZOOM.

If you would like a link to the meeting please email us at contact@thesaintconstruction.info