Work on Level 5 of the Saint progresses this week.
The focus of work at the site this week will be rebar (steel) installation along with sectional concrete pours on Level 5. W
There will be regular concrete deliveries to the site throughout the week. Rebar deliveries to the site will happen as needed.
We do not expect late evening work, though we note that concrete finishing work may extend into the late afternoon and early evening.
REMINDER:
The next Construction Liaison Meeting will be held this week on Thursday, October 27, at 3 pm via ZOOM.
If you would like a link to the meeting please email us at contact@thesaintconstruction.info