Work set for Saturday, October 29, 2022. 

This week work reached Level 6, as concrete and rebar work got underway on this level  after the completion of the 5th Floor.

This Saturday:

  • There will be crews on site doing work in preparation for next week’s rebar and concrete work as well as general site housekeeping work. 

    Outlook for the week of October 31:

    • Ongoing work on Level 6 will continue through the week, with rebar installation, forming, concrete pouring and finishing. 
    • A base for the Hoist (external construction elevator) will soon be constructed. This will permit the unloading of materials and supplies from delivery trucks directly onto the hoist cars. 

    Construction Liaison Meeting Report:

    Next week we will post a summary report of the October 27 Construction Liasion Meeting.