Work progressing on the 7th Floor at the Saint. 

    Saturday Work – December 3

    • There will be a crew on site this Saturday. They will be doing prepartion work for next week’s Level 7 concrete work. We expect they will also be doing a number of housekeeping tasks around the site.

    Construction Update: 

    • The first slab floor concrete pour for Level 7 has been completed this week. 
    • Next week will see the the second slab floor pour for Level 7. 
    • There will be regular deliveries of concrete and rebar to the site through the week. 
    •  There will be traffic staff and a paid duty Police Officer on site as required, to assist with traffic management. 
    • Work is not expected to go past 7 pm for the balance of the week, but we do expect work to continue past the effective 5 pm sunset.

    Our next Construction Liaison Meeting will be held on January 26, 2023 at 3 pm
    via ZOOM

    Happy Holidays.