— Holiday Work Schedule for the Saint.
Days closed and open for work at the Saint over the holiday period:
- Saturday, December 24, 2022 – site closed for Christmas Eve
- Sunday, December 25, 2022 – site closed for Christmas Day
- Monday, December 26, 2022 – site closed for Boxing Day
- Tuesday, December 27, 2022 – site closed for in lieu Statutory Holiday.
- Wednesday, December 28, 2022 – site open for a full workday
- Thursday, December 29, 2022 – site open for a full workday
- Friday December 30, 2022 – site open for a full workday
- Saturday, December 31, 2022 – site closed for New Year’s Eve
- Sunday, January 1, 2023 – site closed for New Year’s Day
- Monday, January 2, 2023 – site closed
- Tuesday, January 3, 2022 – site reopens for a full workday.
Focus of work over the Holidays and for the first week of January 2023:
- Work on forming, installing rebar and pouring the 8th Floor slab and the 8th Floor vertical columns and walls.
- Some interior work and general site housekeeping on the working days between Christmas and New Year’s.
- During the first week of January work toward the completion of the 8th floor is expected to continue.
- Concrete deliveries to the site will occur on all days concrete is being poured.
- Masonary work on the exterior and interior is also expected to be ongoing through the first week of January.
____________________________
Regular Construction Updates will resume in the first week of January.
____________________________
Wishing you a safe and Happy Holiday, and Best for the New Year.
____________________________