— Holiday Work Schedule for the Saint. 

    Days closed and open for work at the Saint over the holiday period:

      • Saturday, December 24, 2022 – site closed for Christmas Eve
      • Sunday, December 25, 2022 – site closed for Christmas Day
      • Monday, December 26, 2022 – site closed for Boxing Day
      • Tuesday, December 27, 2022 – site closed for in lieu Statutory Holiday. 
      • Wednesday, December 28, 2022 – site open for a full workday
      • Thursday, December 29, 2022 – site open for a full workday
      • Friday December 30, 2022 – site open for a full workday
      • Saturday, December 31, 2022 – site closed for New Year’s Eve
      • Sunday, January 1, 2023 – site closed for New Year’s Day
      • Monday, January 2, 2023 – site closed
      • Tuesday, January 3, 2022 – site reopens for a full workday. 

      Focus of work over the Holidays and for the first week of January 2023: 

        • Work on forming, installing rebar and pouring the 8th Floor slab and the 8th Floor vertical columns and walls. 
        • Some interior work and general site housekeeping on the working days between Christmas and New Year’s. 
        • During the first week of January work toward the completion of the 8th floor is expected to continue.
        • Concrete deliveries to the site will occur on all days concrete is being poured. 
        • Masonary work on the exterior and interior is also expected to be ongoing through the first week of January. 
        ____________________________
         
        Regular Construction Updates will resume in the first week of January.