Construction Information Contact Us Home Construction Updates FAQ The Project Concrete Work Contact Us About — Work on the 10th floor is the focus of work this week.  The Week of Janaury 30, 2023 Forming, rebar installation and concrete work will be focused on...
Construction Update for January 13, 2023

Construction Update for January 13, 2023

Construction Information Contact Us Home Construction Updates FAQ The Project Concrete Work Contact Us About  — Moving ahead on the 9th Floor at the Saint.  Work next week at the Saint: Pouring the Level 9 concrete slab floor is set to get underway this coming...
Construction at the Saint, January 3, 2023.

Construction at the Saint, January 3, 2023.

Construction Information Contact Us Home Construction Updates FAQ The Project Concrete Work Contact Us About — Our first 2023 Update for the Saint.  Work this week at the Saint: The 8th Floor slab is expected to be complete by Wednesday, January 4. Work on the...