— Our first 2023 Update for the Saint.

Work this week at the Saint:
- The 8th Floor slab is expected to be complete by Wednesday, January 4.
- Work on the 9th floor is set to get underway by Thursday, January 5.
- Work on the 9th Floor will involve forming, then pouring vertical columns and walls. Slab floor work, forming, rebar installation, concrete pouring and concrete finishing.
- Truck deliveries will follow the pattern of work, with concrete deliveries to be expected daily, Monday through Friday, and rebar (steel) deliveries as needed for each phase of the Level 9 build out.
- We expect there will be a crew on site on Saturday, January 7, conducting the usual mix of ‘Saturday Work’:
- Preparation work for the coming week.
- Interior work on the lower floors.
- General site housekeeping.

____________________________
The next Construction Liaison Meeting will be held on Thursday, January 26, at 3 pm, via Zoom.
____________________________
Best Wishes for the New Year.
____________________________