— Moving ahead on the 9th Floor at the Saint.

Work next week at the Saint:
- Pouring the Level 9 concrete slab floor is set to get underway this coming week.
- 2 rebar (steel) deliveries and 2 concrete deliveries are scheduled for the week.
Saturday, Janaury 14:
- Depending on weather conditions there may be a crew on site tomorrow, Saturday, January 14, conducting the usual mix of ‘Saturday Work’:
- Preparation work for the coming week.
- Interior work on the lower floors.
- General site housekeeping.

____________________________
The next Construction Liaison Meeting will be held on Thursday, January 26, at 3 pm, via Zoom.