— Moving ahead on the 9th Floor at the Saint. 

    Work next week at the Saint:

      • Pouring the Level 9 concrete slab floor is set to get underway this coming week.  
      • 2 rebar (steel) deliveries and 2 concrete deliveries are scheduled for the week.

      Saturday, Janaury 14:

      • Depending on weather conditions there may be a crew on site tomorrow, Saturday, January 14, conducting the usual mix of ‘Saturday Work’: 
        • Preparation work for the coming week. 
        • Interior work on the lower floors. 
        • General site housekeeping.
      ____________________________
       
      The next Construction Liaison Meeting will be held on Thursday, January 26, at 3 pm, via Zoom. 