— Work on the 10th Floor Slab gets underway on Monday.
Progress on the build out of the 9th Floor and the columns rising from the 9th Floor to the 10th Floor is complete. Preparation work for the 10th Floor slab has been completed.
Saturday, February 11:
- We do not expect there to be any signifcant work this Satruday. However, there may be a small contingent of workers on site doing some hosuekeeping work.
REMINDER:
The next Construction Liaison Meeting will be held on Thursday, February 23, at 3 pm, via Zoom.
Work next week at the Saint:
- Pouring the 10th Floor slab.
- Additional Forming a smaybe required.
- Rebar installation.
- Concrete pouring.
- Concrete finishing.
- There will be concrete deliveries to the site to support the 10th Floor work.
- Interior work is ongoing on the lower floors.
- Window instalation is set to begin by the end of February