— Work on the 11th Floor gets underway next week.
A small crew will be on site this Saturday, February 18.
They will be focused on preparation work for next week.
Work on the 11th Floor Slab gets underway on Monday, February 20.
Progress on the build out of the 10th Floor is substantially complete.
The focus of the coming week will be pouring the 11th Floor concrete slab floor.
The delivery of exterior windows will get underway on Tuesday, February 21.
We expect two major concrete deliveries through the week and two rebar deliveries.
Traffic staff and a Paid Duty Police Officer will be on site to manage traffic flows.