Construction Liaison Meeting New Date:
Thursday, March 30, at 3 pm. 

    Saturday Work at the Saint.

    We expect that a work crew will be on site March 25, doing general housekeeping and preparatory work throughout the building. 

    ______________________________


    Construction Update & Highlights for the Week of March 27: 

    • Ongoing work on the Level 12 concrete slab.
    • The Level 2 windows are now 80% complete.
    • We expect that the Level 3 windows will be complete end of coming week.
    • The installation of interior corridor walls is set to begin in April.
    • The Hoist (external construction elevaor) will be raised to the 14th floor to accomodate the growing height of the building.

    Traffic staff and a Paid Duty Police Officer will be on site to manage traffic flows.

     

    New Date:

    The next Construction Liaison Meeting
    will be held on Thursday,
    March 30, at 3 pm, via Zoom.