Saturday Work, April 22.
Construction Liaison Mtg – 3 pm, Thursday, April 27.
Update:
The hoist (external construction elevators) has been raised to the 9th Floor of the building.
There will be a crew on site this Saturday, April 22 working on preparation for the coming week and general housekeeping tasks throughout the site.
Window installation has reached Level 6.
______________________________
Concrete Work for the week of April 24:
Work will begin this coming week on the 14th Floor concrete slab:
- This involves forming, setting rebar, pouring concrete and then finishing that poured concrete.
- Concrete and rebar deliveries will support this work.
- Concrete finishing, as noted, will follow the pouring of concrete, and in some cases may stretch into the late afternoon or early evening.
NOTE: We will provide an update on Friday regarding weekend activity, if there is any scheduled.
Other work this coming week:
- Window installation will move from Level 6 upwards this coming week and the following week.
- The installation of interior corridor walls is underway.
- As windows are completed suite work will get underway, with initial work on installing studs, installing electrical and plumbing.
Deliveries for the week of April 24:
- We expect a maximum of two (2) Window deliveries this coming week.
- We expect a maximum of two (2) concrete deliveries this coming week.
- There may also be a maximum of two (2) rebar (steel) deliveries.
If there are significant changes to planned construction activity, we will post and circulate an update during the week.
NOTE: Three (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.
April 2023 Construction Liaison Meeting