Update:

There will be a crew on site this Saturday, May 6 working on preparation for the coming week and general housekeeping tasks throughout the site. 

Overall: 

Window work is now at Level 6.

The concrete for Level 14 is substantially complete.

NOTE: In recent weeks, several days of exterior work have been lost to rain. This has slowed progress particularly on concrete work. With a better forecast ahead it is hoped that the coming week will proceed as planned.  

______________________________

Concrete Work for the week of May 8:

Work will be focussed on the 15th Floor:

  • This involves forming, setting rebar, pouring concrete and then finishing that poured concrete.
  • Concrete and rebar deliveries will support this work. 
  • Concrete finishing, as noted, will follow the pouring of concrete, and in some cases may stretch into the late afternoon or early evening.

NOTE: We will provide an update on Friday regarding weekend activity, if there is any scheduled. 

Other work this coming week:

  • Window installation will continue to progress above Level 6 upwards.
  • Stud work is ongoing in the interior corridors.

Deliveries for the week of May 8:

  • We expect a maximum of two (2) Window deliveries this coming week.
  • We expect a maximum of two (2) concrete deliveries this coming week.
  • There may also be a maximum of two (2) rebar (steel) deliveries. 

If there are significant changes to planned construction activity, we will post and circulate an update during the week. 

NOTE: Three (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.