Work this Saturday, June 10 at the Saint.

June 10, 2023:

There will be a crew on-site this Saturday working on preparation for next week and general housekeeping tasks.

Work Outlook for the week of June 12 – June 16: 

  • Crews are continuing to work to complete the Level 18 concrete and rebar (steel) work through the week.
  • Window installation work is currently on levels 7 & 8 and will continue into the coming week.
  • Interior work and mechanical/electrical are ongoing in the podium levels of the building. 
  • The hoist (external construction elevator) will be raised mid-June to accommodate the growing height of the building. 

______________________________

Deliveries for the week of June 12:

  • We expect a maximum of two (2) Window deliveries this coming week.
  • We expect a maximum of two (2) concrete deliveries this coming week.
  • There may also be a maximum of two (2) rebar (steel) deliveries. 

If there are significant changes to planned construction activity, we will post and circulate an update during the week. 

NOTE: Three (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

Construction Liaison Meeting

Note: we will be confirming next week if the planned Construction Liasion meeting will occur on June 22 or be rescheduled. 

The next Construction Liaison Meeting is currently planned to be held on

Thursday, June 22, at 3 pm, via Zoom.