Work this Saturday, June 17 at the Saint.
June 29 Construction Liaison Meeting
June 17, 2023:
There will be a crew on-site this Saturday working on preparation for next week and general housekeeping tasks.
Work Outlook for the week of June 19 – June 23:
- Crews are continuing are set to complete the Level 19 concrete and rebar work by the end of the week.
- Window installation work is currently on Level 7 and Level 8 and will continue into the coming week.
- Ground Floor window installation is underway.
- Interior work and mechanical/electrical are ongoing in the podium levels of the building.
______________________________
Deliveries for the week of June 19:
- We expect a maximum of two (2) Window deliveries this coming week.
- We expect a maximum of two (2) concrete deliveries this coming week.
- There may also be a maximum of two (2) rebar (steel) deliveries.
If there are significant changes to planned construction activity, we will post and circulate an update during the week.
NOTE: Three (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.
New Date: Construction Liaison Meeting