Work this Saturday, June 17 at the Saint.
June 29 Construction Liaison Meeting

June 17, 2023:

There will be a crew on-site this Saturday working on preparation for next week and general housekeeping tasks.

Work Outlook for the week of June 19 – June 23: 

  • Crews are continuing are set to complete the Level 19 concrete and rebar work by the end of the week. 
  • Window installation work is currently on Level 7 and Level 8 and will continue into the coming week.
  • Ground Floor window installation is underway. 
  • Interior work and mechanical/electrical are ongoing in the podium levels of the building. 

______________________________

Deliveries for the week of June 19:

  • We expect a maximum of two (2) Window deliveries this coming week.
  • We expect a maximum of two (2) concrete deliveries this coming week.
  • There may also be a maximum of two (2) rebar (steel) deliveries. 

If there are significant changes to planned construction activity, we will post and circulate an update during the week. 

NOTE: Three (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

New Date: Construction Liaison Meeting

The next Construction Liaison Meeting will be held on

Thursday, June 29, at 3 pm, via Zoom.