July 28 Construction Update

July 28 Construction Update

The Saint: work on the 23rd Floor set for the coming week. Saturday Work There will be a crew on site, Saturday, July 29, working on a variety of tasks throughout the site.    Outlook for the week of July 31 – August 4 Crews will begin working on rebar...
July 20 Construction Update for the Saint

July 20 Construction Update for the Saint

The Saint nearing completion of concrete for the 22nd Floor. Saturday Work There will be a crew on site, Saturday, July 22, working on a variety of tasks throughout the site.      Work Outlook for the week of July 24 – 28 Crews will be working to...
The Saint Construction Update July 14, 2023

The Saint Construction Update July 14, 2023

The Saint heading up to the the 21st Floor. Saturday Work There will be a crew on site, Saturday, July 15, working on variety of tasks throughout the site.  Work Outlook for the week of July 17 – 21 Crews will be working on forming, rebar installation and...
The Saint Construction Update July 7, 2023

The Saint Construction Update July 7, 2023

The Saint has reached the 20th Floor. Saturday Work There will be a crew on site, tomorrow, Saturday, July 8, working on variety of tasks throughout the site.  Work Outlook for the week of July 10 – 14 Crews will be completing concrete work on Level 20. Window...