by admin | Jul 28, 2023 | Construction Updates
The Saint: work on the 23rd Floor set for the coming week. Saturday Work There will be a crew on site, Saturday, July 29, working on a variety of tasks throughout the site. Outlook for the week of July 31 – August 4 Crews will begin working on rebar...
by admin | Jul 20, 2023 | Construction Updates
The Saint nearing completion of concrete for the 22nd Floor. Saturday Work There will be a crew on site, Saturday, July 22, working on a variety of tasks throughout the site. Work Outlook for the week of July 24 – 28 Crews will be working to...
by admin | Jul 13, 2023 | Construction Updates
The Saint heading up to the the 21st Floor. Saturday Work There will be a crew on site, Saturday, July 15, working on variety of tasks throughout the site. Work Outlook for the week of July 17 – 21 Crews will be working on forming, rebar installation and...
by admin | Jul 7, 2023 | Construction Updates
The Saint has reached the 20th Floor. Saturday Work There will be a crew on site, tomorrow, Saturday, July 8, working on variety of tasks throughout the site. Work Outlook for the week of July 10 – 14 Crews will be completing concrete work on Level 20. Window...