Saturday Work

There will be a crew on site, Saturday, July 15, working on variety of tasks throughout the site. 

Work Outlook for the week of July 17 – 21

    • Crews will be working on forming, rebar installation and concrete pours for Level 21.
    • Window installation will be active on Level 8 and the Ground Floor, through the coming week.
    • The Hoist (external construction elevator) is in regular opertation to Level 15.
    • Corridor layout and related work is active on the interiors of the podoium levels.

 

______________________________

Deliveries for the week of July 17

  • We expect a maximum of two (2) Window deliveries this coming week.
  • We expect a maximum of two (2) concrete deliveries this coming week.
  • There may also be a maximum of two (2) rebar (steel) deliveries. 

If there are significant changes to planned construction activity, we will post and circulate an update during the week. 

NOTE: Three (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

Summer Construction Liaison Meeting

August 3, 2023 at 3 pm

Per the resutls of our Doodle Poll with regular attendees, the next meeting will ne held at 3 pm on Thursday, August 3 via ZOOM. If you have not been a regular attendee but are interested in attending please email us at contact@thesaintconstruction.info for a link to the meeting.