The Saint: work begins on the 24th Floor next week.
Saturday Work:
There will be a crew on this Saturday, August 12, carrying out a variety of tasks.
Outlook for the week of August 14 – August 19:
- Crews will begin working on forming, rebar installation and concrete pours for Level 24.
- Window installation will get underway for Level 12.
- The Hoist (external construction elevators) is to be extended to level 18.
- Corridor layout, suite finishing and related work will be active on the interiors of the lower floors of the building.
______________________________
Deliveries for the week of August 14th
- There are two (2) Window deliveries scheduled this coming week.
- There are two (2) Concrete deliveries scheduled this coming week.
- There are two (2) Steel (rebar) deliveries scheduled this coming week.
- There are two (2) Drywall deliveries scheduled this coming week.
- There is one (1) Carpentry supply delivery scheduled this coming week.
If there are significant changes to planned construction activity, we will post and circulate an update during the week.
NOTE: Three (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.
Next Construction Liaison Meeting
We will be setting a date for the next meeting in the coming weeks.
Per the resutls of our next Doodle Poll with regular attendees, we will target a 3 pm on Thursday, meeting in mid September, via, ZOOM. If you have not been a regular attendee but are interested in attending please email us at contact@thesaintconstruction.info for a link to the meeting.