The Saint: work will begin on the 26th Floor next week.  

Saturday Work:

There will be a crew on this Saturday, August 26, carrying out a variety of tasks.

 

Outlook for the week of August 28 – September 1:

    • Crews will begin forming, installing rebar, pouring & finishing concrete on Level 26 this week.

    • Window installation is now active on Level 14.

    • Interior work ongoing throughout the lower floors of the building. 

    • The Hoist (external construction elevator) will be raised to service Level 23 in early September.

______________________________

Deliveries for the week of August 28th

  • There are two (2) Window deliveries scheduled this coming week.
  • There are two (2) Concrete deliveries scheduled this coming week.
  • There are two (2) Steel (rebar) deliveries scheduled this coming week.
  • There are two (2) Drywall deliveries scheduled this coming week.
  • There is one (1) Carpentry supply delivery scheduled this coming week.

If there are significant changes to planned construction activity, we will post and circulate an update during the week. 

NOTE: Three (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

Next Construction Liaison Meeting

 

We will be setting a date for the next meeting in the coming weeks.

Per the resutls of our next Doodle Poll with regular attendees, we will target a 3 pm on Thursday, meeting in mid September, via, ZOOM. If you have not been a regular attendee but are interested in attending please email us at contact@thesaintconstruction.info for a link to the meeting.