Concrete Pouring on the 26th Floor September 5th – 8th.  

Saturday Work:

There will be a crew on this Saturday, September 2, carrying out a variety of tasks.

Site Closed – Labour Day,
Monday, September 4th

Outlook for the week of
September 5 – 8:

    • Crews will be pouring & finishing concrete on Level 26 this week.

    • Window installation is now active on Level 17.

    • Interior work ongoing throughout the lower floors of the building. 

Deliveries for the week of September 5th: 

  • We expect up to two (2) Window deliveries scheduled this week.
  • We expect up to two (2) Concrete deliveries scheduled this week.
  • We expect up to two (2) Steel (rebar) deliveries scheduled this week.
  • There may also be  a drywall delivery scheduled this week.
  • There may also be other material deliveries this week.

If there are significant changes to planned construction activity, we will post and circulate an update during the week. 

NOTE: Three (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

Crane Lights

As we noted in our previous post, the crane lights were left on overnight in error this past week. This error has been reviewed with the concrete finsihing subcontractor.  Steps are being taken to ensure this does not occur again. 

Next Construction Liaison Meeting

 

We will be setting a date for the next meeting after the Labour Day Weekend

Per the resutls of our next Doodle Poll with regular attendees, we will target a 3 pm on Thursday, meeting after September 12th, via, ZOOM. If you have not been a regular attendee but are interested in attending please email us at contact@thesaintconstruction.info for a link to the meeting.