Work is moving to the 38th Floor at the Saint.  

Saturday Work

A crew will be on site this Saturday, December 9.

 

Current Construction  Status 

  • The Level 37 concrete slab floor is set to be completed by the end of the work day on Friday, December 8. 
  • The elevators to the underground parking levels have been completed. 
  • Curtain Wall installation has reached the 25th floor. 
  • Window Wall installation has reached the 18th floor. 
  • The Hoist (external construction elevators) are operational to the 31st Floor.

Outlook for the Week of December 11th:

  • Work on the Level 38 concrete slab floor will get underway this week.
  • Curtain Wall window installation will be active on Level 26.
  • Window Wall window installation will be active on Level 18.
  • Corridor stud installation will be active on Level 17.
  • Interior suite stud installation will be active on Level 8.
    • Looking ahead:
    • The internal Tower Elevators are set to begin being installed next month.

A note on trucks & deliveries on Lombard Street.

On occasion the site will have 3 trucks, 1 delivery truck and 2 concrete trucks, arrive for unloading at the same time. Minto realizes this presents a further challenge to the movement of traffic on Lombard Street. Every effort is made to avoid this eventuality, however, Minto’s construction management team does not have full control of when deliveries arrive. If and when, for example, a drywall delivery arrives at the same time as a concrete truck, while there is already an initial concrete truck unloading into the concrete pump, there will be an unavoidable impact on the north lanes of Lombard Street. If Minto were to make a habit of turning away one of the concrete trucks in a situation like this, it would cause significant delays in completing the building and therefore extend the construction period, ultimately creating more impact on the immediate area for everyone. 

We also note that the Paid Duty Officer has discretion to make decisions on traffic flow as he or she determines is best for safety and the movement of vehicles and pedestrians. Minto does not have the authority to direct or instruct the Paid Duty Officer.  

A reminder about Concrete Finishing in cold weather.

As we have noted previously, cold weather affects the concrete work. The active temperature requires different mixes of aggregate and different, most often longer, curing and setting times. This impacts the time required to ‘finish’ the concrete, which is the final and a critical part of all continuous concrete pours.

As the temperatures have lowered again, there will be later working hours for concrete finishing. This also means the crane lights will stay on later to ensure the safety of the crews working on the top level of the building. For example, if temperatures are below freezing concrete work is likely to continue to 11 pm or later. To ensure the safety and feasibility of this critical work, the crane lights will stay on until the work is being completed. 

NOTE: This past week the timer on the crane lights failed. It is being replaced, and concrete finishing crews have been reminded to turn off these lights manually, as may be necessary, when their work is completed. 

Deliveries expected for the week of December 11th: 

  • We expect five (5) Concrete deliveries  this week.
  • We expect four (4) Steel (rebar) deliveries this week.
  • There will be two (2) drywall deliveries this week.
  • There will be two (2) window deliveries his week.
  • There will be one (1) carpentry delivery this week
  • There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.
  • If there are significant changes to planned construction activity, we will post and circulate an update during the week.

Holiday Work Hours

At present, the site is set to be open through the holidays, with the site closed on Sunday, December 24, the Statutory Holidays of December 25, 26, Sunday December 31, and New Year’s Day, January 1, 2024. We will update this information if it changes.

Next Construction Liaison Meeting

At the November 30 Meeting it was decided that the next meeting will be held in January, 2024. We will send out notice of the date early in the New Year. 

    If you have not been a regular attendee but are interested in attending please send us an email at contact@thesaintconstruction.info for a link to the meeting.