The Saint heads to 43 storeys this week. 

Saturday Work

A crew will be on site this Saturday, February 3, doing a variety of tasks.

 

Current Construction  Status 

  • Concrete work on Level 42 is complete.
  • The Curtain Wall installation has reached the 26th floor. 
  • Window Wall installation is complete to the 22nd floor. 
  • The elevator components for the main interior elevators have been delivered

This week’s construction outlook, Jan 29 – Feb 3:

  • Concrete pouring for the Level 43 slab floor will be the focus of the week, with completion expected by Friday.
  • Curtain Wall window installation continues on Level 27
  • Window Wall window installation continues on Level 23.
  • Corridor stud installation will be active on Level 20.
  • Interior suite stud installation will be active on Level 11.

Deliveries the week of January 29 – February 3:

  • We expect up to three (3) Concrete deliveries this week.
  • We expect two (2) Steel (rebar) deliveries this week.
  • We expect one (1) or two (2) drywall deliveries this week.
  • We expect two (2) window deliveries this week.
  • There may also be one (1) carpentry delivery this week. 
  • There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

February Construction Liaison Meeting

We have scheduled the next meeting for Thursday, February 22 at 3 pm. A ZOOM Link for the meeting will be sent to those on our list prior to the meeting.